progress in 2006
Progress By Year: 2009 2008 2007 2006 2005
November 2006
Drainage study for land preparation underway;
Mylar maps under development prepatory to planned December submission for zoning change.
October 2006
Traffic impact study completedy
September 2006
Traffic impact study required to gain county approvals underway
August 2006
West Maui Improvement Foundation receives the $30,000 contribution from Florida foundation, largest ever, and an additional $15,000 from another major donor.
July 2006
Right Hospital, Wrong Place: Foundation takes position on proposed hospital in Kihea
Funds for traffic impact study--last of the environmental studies--become available
June 2006
Funds for traffic impact study--last of the environmental studies--become available
April 2006
WMIF issues progress report.(pdf file)
March 2006
On-going discussions continue to gain consensus on a West Maui Hospital solution.
February 2006
Dr. Philip Fagan, a specialist in running acute care emergency rooms, and Alan Richman
review progress in putting together a final agreement to secure hospital financing.
See story on West Maui Taxpayers Assn. Annual Meeting in Maui News.
January 2006
Environmental Assessment work underway at Lahaina Civic Center site
for planned completion in April.